Detailed below are the supplies we require and the schedule for fixing the wall of the dojo along with cleaning and painting.
Supplies:
For the Wall:
Need to purchase:
6 sheets of plywood (estimated, should measure and possibly revise)
Screws
Need to borrow:
Screw guns (maybe 3-4)
For Cleaning:
Need to purchase:
Dust Masks
Sponges on sticks (everything is better on a stick)
Cloths
Need to borrow:
Steam cleaner (Dennis?)
Ladders (Skip and Zach)
For Painting:
Need to purchase:
Paint (need to determine how much)
Rollers
Brushes
Masking Tape
Drop cloths (hopefully we can borrow these)
Schedule:
Friday:
Perhaps a special class starting early
After class remove everything from walls and storage and place on ground/mat
Saturday:
Move everything from ground/mat to parking lot
Step 1:
Cleaning crew begins to clean the walls, steam the carpets and drapes, wipe down couches, pine-sol wood, and clean the storage area
Demo crew knocks out the wall
Step 2:
Painting crew begins to paint the walls
Building crew hangs the plywood
Step 3:
Once the plywood is hung and painting is finished everything must be moved back in from the parking lot
In the evening possible second coat if required
Sunday:
Touch ups if necessary
Rehang and store everything
Finish cleaning and perhaps mop the floors
Optional:
This may also be a good time to install the mirror everyone has been talking about
Rather than rehanging the old boards, we can take this opportunity to update and add other boards
What must be done before we can get to work:
We need to figure out how to procure all of the supplies we require (commit to lending, donating, or using dojo funds)
We need to set a date for this to occur
Post questions, comments, suggestions, and possible dates in the accompanying forum post. Lets make this happen!
Read original blog post